Here is an update on the exciting work being done at the new building site: 

  1. Classroom Building structure installation is about 50% complete. Framing is also in progress.
  2. Worship Center framing and fire sprinklers are in progress. HVAC units are being installed.
  3. 90% of our underground utility work is complete.

For more information on the building project, check of graceforgenerations.org

 